@@ -21,7 +21,7 @@ Each gate produces evidence and an explicit GO, PAUSE or BLOCKED result.
| Stage 7 observation archive | GO (point/pose/telemetry contract) — durable catalog, recovery, capture-clock-bounded RRD preparation, archived metric time series, saved-session timeline and atomic playback are implemented |
| Stage 7 recorded cameras | GO (contract), acceptance pending — acquisition-owned fMP4 archive and player are implemented/tested; one real archived K1 camera plus point-cloud session has not passed playback yet |
| Plugin isolation | GO (laboratory control plane) — vendor backend/frontend and optional scene controls are plugin-owned; manifest/runtime descriptor parity, versioned handshake, lifecycle health and transport correlation fail closed while execution remains in-process |
| K1 application control | PAUSE (accepted START followed by `ALGORITHM_ERROR`) — first live attempt stopped before START on a batch-3 correlation failure; a second attempt correlated all 10 pre-START requests plus START but collapsed UI stages into 365 ms and omitted the retained post-START/control-session lifecycle. The collapsed path and standalone START/STOP are disabled. An uninstalled offline executor now uses explicit UI checkpoints plus live DeviceStatus gates; no further physical write is authorized yet |
| K1 application control | OPERATOR ACCEPTANCE READY — the failed collapsed path and standalone START/STOP remain disabled. Plugin v0.5.0 installs one continuous control-session owner behind separate connection, workspace, project, START, STOP and steady-green UI actions. No wall-clock transition, automatic retry, navigation-triggered command or repository-test equipment I/O exists. A full operator-run physical cycle and native-project verification remain open |
| Stage 8 product storage | PAUSE — retention, replication, encryption, capacity monitoring and long-run browser/WASM stress remain deployment gates |
USB project copying remains optional ground truth rather than a blocker for the